Rendering of planned Bell School AdditionKeep up with the latest news about Bell's addition as it moves from design and planning to construction. To read more about the project, visit the Public Building Commission's Bell School page.



Construction Begins! PDF Print E-mail

We are excited to announce that the permits for our addition have been attained, so work will officially begin on Monday, May 13, 2013.  Com Ed will be here on Monday to provide power for the project.  This marks the beginning of a very exciting time at Bell School.  We will continue to provide updates as they become available.

 
Contract Awarded PDF Print E-mail

The Public Building Commission has awarded the contract for the Bell School addition to Wight Construction Services. Construction fences were installed place on Friday, April 19 and work is expected to begin shortly thereafter.

 
Bids Opened PDF Print E-mail

The Bell School Addition construction project went out to bid and all bids submitted were over budget. The Public Building Commission is looking at cost reduction and will be reissuing the bid shortly. The PBC plans to award the bid to a contractor in March, with construction to begin immediately after. The PBC has assured us the priority is the addition and there is no intent to change the programmatic design.

 
Bidding Closed December 18 PDF Print E-mail

The Public Building Commission (PBC) held a contractor walk-through of Bell School on Wednesday, December 5, 2012. Nine firms were pre-qualified for the project. The bid closd on Tuesday, December 18, 2012, at which time bids were publicly opened.

Last Updated on Thursday, 10 January 2013 13:27
 
Addition Plans Online PDF Print E-mail

Plans for Bell's new addition were on display Thursday, October 25, at a community meeting held at Bell School. If you missed the meeting, the presentation is now available on the Public Building Commission's page for the Bell project.

Last Updated on Thursday, 01 November 2012 13:52
 
Construction Schedule PDF Print E-mail

Bell School is receiving an addition to the south end of the building. The project is under the direction of the Public Building Commission (PBC).  The current schedule has the project going out for bid in November 2012 and construction starting in Spring 2013 when weather permits. 

The project scope is as follows: a new addition with a cafeteria/multipurpose space, cooking kitchen, new science lab, new art classroom, new music room. The cafeteria/multipurpose room will be a taller volume space that allows for use for athletics. In the existing building, the renovation includes moving the library and nursing office into the current lunchroom; repair and refinishing of the existing gym floor; plumbing upgrades including new distribution piping and bathroom renovations; conversion of the old art room and into classrooms; renovation of the old music room; aisle and emergency lighting in auditorium; and renovation of a third floor science lab.

Project completion, including renovation of the existing building, is expected by February 2014. Once the project is complete, the new ancillary rooms will allow improved space utilization in the existing building. This includes the creation of a second art room in a classroom with a sink and an additional music room. Those moves will take place by the beginning of the 2014-2015 school year.

Here is a list of areas and when they will be complete by phase.

Spring 2013 – Start of addition work

Summer 2013 – No summer school can be held at Bell this year – new plumbing risers, bathroom renovations within the existing building, gym floor refurbishment, aisle and emergency lighting in the auditorium, renovating of music room, boiler room work, MDF/IDF connection work, some intercom work.

January 2014 – Addition opens for winter semester.

January 2014 – Renovation of existing art room, construction of library and nursing office in existing lunchroom will occur during evening hours when students are not present.

February 2014 – Renovation of existing library into a classroom and completion of construction punch list tasks.